Project/Contract: Finishing of special surgery building in Shifa hospital

Client: Qatar Red Crescent QRC  
Owner
: Ministry of Health

Saqqa & Khoudary started the implementation of this 'extraordinary' hospital in March, 2011. The works are primarily electrical and mechanical works including heating, ventilation, and air conditioning systems, chillers, air handling units, fan coil units, medical gases system, water supply system, fire fighting system, elevators, 3.5 MW synchronised generators, fuel supply system, transformers, equipping of surgery and operation rooms, building control systems etc. These are besides all civil, finishing and decoration works in order to deliver the buildings in ‘operating’ state. The surgery building has 6 operation theatres and 140 patient beds. The hospital testing, commissioning and handing over processes were undertaken in May 2014.  