Ras Al Taweel & Al ‘Uddeisa Water Infrastructure Phase 1A and Al Safi Booster Station – Phase I Pipeline Connection

 Client: USAID
Saqqa & Khoudary signed the multi-million contract in October, 2014. The objective of this Task Order is to improve water supply distribution capacity and flexibility in the West Bank Water Department’s (WBWD) southern area of operations. Specifically the project will improve distribution of water from the Halhul Reservoir and improve supply to Bani Naim and Yatta. This project scope includes the construction of 5 km of 500-mm diameter steel pipe transmission main, 5 km of 150-mm diameter steel pipe supply pipeline, service connections, flow meter vaults, booster stations refurbishment and upgrading including piping, valves, SCADA system.  

Visits: 16