New Projects

Project/Contract: Design and Construction of Wadi Gaza Interim Wastewater Treatment Plant

Client: International Committee of the Red Cross (ICRC) Owner: Coastal Municipalities Water Utility (CMWU)   Saqqa & Khoudary won the Design and Build contract in August, 2012. The contract includes design, engineering, construction, supply, install, commissioning and start-up of the plant based on lagoon-based treatment on a total area of 32,000 m2. The plant has a capacity of 14,000 m3/day or 240,000 PE   The works include excavation, earthworks and embankment construction for the ...

Sheikh Hamad Hospital for Rehabilitation and Prosthetic Limbs

Client: Gaza Reconstruction Committee- State of Qatar Owner: Ministry of Health   The contract was awarded to Saqqa & Khoudary in November, 2013 and is expected to takes 2 years time to be accomplished.  This prestigious hospital consists of basement and 5 floors, group, semi-private and private rooms for patients, besides admin building, landscape and other facilities. The site area is 13,000 m2 In addition to the structural construction, finishing and decoration works, there are heavy ...

Construction of Turkey- Palestine friendship hospital in Gaza

Client: AKER Owner: Islamic University of GazaIn June, 2011, Saqqa & Khoudary started the construction of the largest single-site hospital in the country. The hospital was built on a total land area of 35,000 m2, with a capacity of 115 patient beds. The works include construction and finishing of all hospital’s reinforced concrete buildings, retaining structures, boundary walls, water tank, electro-mechanical works and equipping the hospital. Heavy electro-mechanical installations include ...

Project/Contract: Finishing of special surgery building in Shifa hospital

Client: Qatar Red Crescent QRC  Owner: Ministry of HealthSaqqa & Khoudary started the implementation of this 'extraordinary' hospital in March, 2011. The works are primarily electrical and mechanical works including heating, ventilation, and air conditioning systems, chillers, air handling units, fan coil units, medical gases system, water supply system, fire fighting system, elevators, 3.5 MW synchronised generators, fuel supply system, transformers, equipping of surgery and operation rooms ...

Biddu-Beit Anan Road

 Owner: USAIDThis project consists of constructing, upgrading, paving and milling 2.4 km of the Biddu Beit Anan Road in the Governorate of Jerusalem. The construction started in October, 2013 and finished in July, 2014.     The scope consists of excavation works, embankment filling, pavement layer construction, installation and/or rehabilitation of storm water drainage systems, installation of safety features (signage, road marking, cat eyes, and guardrails) etc ...

Rehabilitation and Expansion of Johr Al Dik dump site

Client: UNDP Owner: Municipality of Gaza SAK won this contract in February 2013. The works are primarily excavations and earthworks for landfill construction, geo-membrane, geo-textile, bentonite mat, drainage layer, HDPE  pipes for leachate collection, gas collection system, concrete works, leachate collection and recirculation, surface water collection (ditches and pond), hazardous waste pond, and road construction.   The landfill was delivered in April, 2014 ...